Project Description
This road safety improvement scheme was necessary as the existing N17/R320 junction and immediate vicinity have been the scene of many collisions, some fatal, in recent years and has been identified as a high collision location by Transport Infrastructure Ireland.
The Project comprised an upgrade of the existing at-grade junction of the N17 National Road with the R320 Regional Road to a compact grade separated junction and includes:
- Realignment of existing N17 West junction with R320 Regional Road to form a compact connector road;
- Provision of N17 East junction with compact connector road to proposed eastern roundabout;
- Provision of 0.31 km link road including overbridge between existing R320 regional road and proposed eastern roundabout;
- Provision of 0.54 km link to L-5565-0 existing Meelick More Road;
- Overbridge structure to be constructed over the existing N17 to carry the proposed R320 Link;Provision of 2 no. roundabouts on existing R320 regional road (western roundabout) and at junction of N17 East compact connector, L-5565-0 Link and R320 Link (eastern roundabout);
- Provision of approximately 0.89 km of a Shared Footway / Cycleway;
- Provision of local collector road for properties on north side of L-5565-0 Meelick More Road with one junction on realigned L-5565-0, and
- Closure of the existing N17/L-5565-0 Meelick More Road junction.
Current Project Phase
The project is currently at Phase 7 (Complete) of the TII Project Management Guidelines.
The main construction contract was awarded to Contractor BAM Civil Ltd. on 22nd November 2021 and the project was officially opened in July 2023.